Re: Converting Policy Managed RAC to Admin managed Database
From: Hemant K Chitale <hemantkchitale_at_gmail.com>
Date: Mon, 27 Feb 2017 15:35:21 +0800
Message-ID: <CAMNBsZskxmavwWBgBfC=42S8RoUjWferf=vZvwUr+5Kc6wiL+w_at_mail.gmail.com>
Date: Mon, 27 Feb 2017 15:35:21 +0800
Message-ID: <CAMNBsZskxmavwWBgBfC=42S8RoUjWferf=vZvwUr+5Kc6wiL+w_at_mail.gmail.com>
How many databases do you have on the Cluster ? With 4 nodes, I would still have used Admin Managed.
Here's a conversion I did on a 2node cluster for a single database : https://hemantoracledba.blogspot.sg/2017/01/12cr1-rac-posts-3-convert-policymanaged.html
The key steps are to create the parameter file and srvctl add instance.
Hemant K Chitale
On Fri, Feb 24, 2017 at 12:01 PM, Sanjay Mishra <dmarc-noreply_at_freelists.org
> wrote:
> We have currently 4 node Policy Managed RAC and so removing 2 node from
> the cluster due to Licnese and so need to convert the Policy Managed
> database to Admin Managed to be spanned on two final RAC nodes
>
> TIA
> Sanjay
>
-- Hemant K Chitale http://hemantoracledba.blogspot.com http://hemantscribbles.blogspot.com -- http://www.freelists.org/webpage/oracle-lReceived on Mon Feb 27 2017 - 08:35:21 CET