Re: Calculating # of working days in a period.
From: Dave Jordan <jordan_at_pt5026.pto.ford.com>
Date: 1 Nov 1994 14:52:08 GMT
Message-ID: <395kmo$qvk_at_eccdb1.pms.ford.com>
Date: 1 Nov 1994 14:52:08 GMT
Message-ID: <395kmo$qvk_at_eccdb1.pms.ford.com>
Ooops, left distribution local, so here it is again.
Here is a procedure we use to add a given number of working days to the current date:
NAME = workdate
DEFINITION = <<<
FUNCTION workdate (start_date IN date, add_days IN number) return date IS
/* This function adds a number of working days (add_days) */
/* to a date (start_date) and returns it (end_date) */
end_date date;
day_name char(3);
working_days number(5);
dummy date;
CURSOR holiday IS select holiday
from dbs.ford_holidays
where holiday = end_date;
BEGIN
working_days := 0;
end_date := start_date;
while (working_days < add_days) LOOP
end_date := end_date + 1;
day_name := to_char(end_date,'DY');
if day_name != 'SAT' and day_name != 'SUN' then
open holiday;
fetch holiday into dummy;
if holiday%NOTFOUND then
working_days := working_days + 1;
end if;
close holiday;
end if;
end LOOP;
return (end_date);
EXCEPTION when OTHERS then null;
END;
>>>
A table holds the holidays, as they change year to year for us. A slight modification to this will allow you to enter the start and end dates and return the number of workdays between. Instead of looping on add_days, loop until end_date and add up the days in the loop.
Dave Jordan Received on Tue Nov 01 1994 - 15:52:08 CET