Oracle FAQ | Your Portal to the Oracle Knowledge Grid |
Home -> Community -> Usenet -> c.d.o.server -> Re: Ora 8i to Ora 9i move; PL/SQL compatibility
On 17 Dec 2002 07:02:27 -0800, cosmini_at_yahoo.com (cosmin ioan) wrote:
>we're trying to move (or rather, run) our many pl/sql packages from
>Ora8i (8.1.6 - 8.1.7) to Ora9i (latest) and are having some problems
>with the code.
>Is there a list of PL/SQL gotchas, things to be aware of when patching
>the backend to latest version?
I've not seen anything that breaks correct code, but the 9i PL/SQL parser is stricter in some areas than the 8i parser so it may flag up some things you've not spotted before.
Two concrete cases I've seen are:
-- Andy Hassall (andy@andyh.org) icq(5747695) http://www.andyh.org http://www.andyhsoftware.co.uk/space | disk usage analysis toolReceived on Tue Dec 17 2002 - 15:12:01 CST