I'm using Oracle 8.1.7.0 on NT. I have a process that submits several
(30 to 40) jobs to be run as soon as possible. My job_queue_processes
is 4 and job_queue_interval is 20. What happens is that all the jobs
are in the queue and 4 start running. Each of the jobs are "finished"
at different times but seem to hang waiting for the longest job to
finish. (I've checked to see if locks are the culprit but it doesn't
seem so). After the 4 jobs are done and removed from the queue, there
is about a 5 MINUTE delay before the next set starts. This continues
until all the jobs are finished. I've checked all the things I know
about over the last 2 or 3 weeks but can't find what's wrong. We went
to 8.1.7 from 8.1.5 and this problem showed up. It worked fine on
8.1.5.
Any insight will be appreciated.
Thanks,
Alton