We are going to convert one of our Oracle application from Version 6.0.33 to 7. We have come up with an eight week estimate for the conversion of:

         27 - 3.0 Forms
          4 - Pro-C Libraries
         20 - SqlPlus reports
         19 - ProC programs

Has anyone else done a conversion from V6 to V7 of this size? Any suggestions? Any input on the time required?

Thank you in advance.

Mark Wilcox                             Voice:303-673-3528 
Storage Technology Corp.                Fax: 303-673-2870
V042562_at_procyon.stortek.com Received on Fri Jul 15 1994 - 18:15:54 CEST