Re: Using DBMS_SCHEDULER to execute a three step job of different type(2 stored procedure and an executable)

From: MTNorman <mtnorman_at_duke-energy.com>
Date: Thu, 19 Jul 2007 03:18:30 -0700
Message-ID: <1184840310.278205.149300@w3g2000hsg.googlegroups.com>


In 10.2, you can use scheduler job chains to create dependencies between a series of jobs. Check out the "Using Chains" section of the 10.2 Admin Guide (b14231).

On Jul 17, 2:34 pm, rateeshmo..._at_gmail.com wrote:
> Hi Guys,
>
> I would like to schedule 3 jobs which should run one after the other.
> The first job is a procedure which when successfully completed should
> invoke a executable from the operating system and once that finishes
> successfully , which can be determined by a return value should invoke
> another stored procedure. How can this be accomplished?
>
> your inputs are highly aprreciated.
>
> Thanks