I am going to restore my PRD (8.1.7) to DEV (9). In my PRD, I have a
full offline backup scheduled in db13 to a DDS-4 tape. With this tape,
I am going to restore PRD to my DEV.
- Remove all the DEV filesystems
- Create the PRD filesystems
- the command used to restore is "brrestore -b
<coded_timestamp>.<fid> -m full". This file <coded_timestamp>.<fid> is
tied to the same one with what is shown in the DB13 log.
- This will restore the complete PRD system. Problem is that this
restored system is a 8.1.7. But the one in DEV is 9 therefore the
binary is different. Hence I need to upgrade this current copy to PRD
by
a. upgrade the cloned 8.1.7 database to 9.2.0 by running
@?/rdbms/admin/u0801070.sql
- In note 592393, it wrote
"Switch from 8.1.7 to 9.x
After the copy, you must execute all of the upgrade steps
described in the
guide for upgrading to Oracle 9.x. "
Please advise.
Received on Tue Nov 02 2004 - 09:28:32 CST