I'd suggest you do a trial run on your development databases (you do have some? perferable ones that have been cloned/renamed from a production copy).
There's a lot that can go wrong if you don't
The migration/upgrade manual should highlight the pros/cons.
"Robert Yeh" <robert.yeh_at_qwest.com> wrote in message
news:9gdoeb$r7o$1_at_bob.news.rcn.net...
> HP unix.
>
> I was told 3-4 hours. Does it really take that long? What are the risks
> involved? How difficult is it to roll it back if the application has
> problems.
>