Resource Manager
From: Lothar Flatz <l.flatz_at_bluewin.ch>
Date: Tue, 14 Apr 2020 16:22:54 +0200
Message-ID: <5dad6add-ff31-035a-ba3d-e5fc68e41fa6_at_bluewin.ch>
Hi,
Date: Tue, 14 Apr 2020 16:22:54 +0200
Message-ID: <5dad6add-ff31-035a-ba3d-e5fc68e41fa6_at_bluewin.ch>
Hi,
Resource Manager Plan is not Set. AWR reports
"SCHEDULER[0x32D9]:DEFAULT_MAINTENANCE_PLAN".
Parameter CPU_COUNT is not set.
My understanding is : Resource Manager is active during maintenance
windows only.
CPU_COUNT will be derived. It does not matter if it is set or not.
Would explicit setting CPU_COUNT activate Resource Manager outside of
maintenance windows?
Would setting CPU_COUNT to the default value (os cores * 2) make a
difference to not setting a value?
Regards
Lothar
-- -- http://www.freelists.org/webpage/oracle-lReceived on Tue Apr 14 2020 - 16:22:54 CEST