Re: Time to upgrade verses size of DB

From: Andrew Kerber <andrew.kerber_at_gmail.com>
Date: Mon, 15 Mar 2010 14:47:55 -0500
Message-ID: <ad3aa4c91003151247j102edf89k29a61207a7c3a682_at_mail.gmail.com>



No, the upgrade time doesn't change based on size. Its pretty much totally dependent upon the horsepower of the Oracle server.

On Mon, Mar 15, 2010 at 2:42 PM, <Joel.Patterson_at_crowley.com> wrote:

>
>
> I didn’t want to open an SR just for this question.
>
>
>
> For downtime scheduling purposes -- Upgrading from Oracle 10.1.0.2, or
> 10.1.0.4 to 10.2.0.4 (on Solaris 5.10, (or any OS)):
>
>
>
> Does the time it takes to upgrade significantly change depending on the
> size of the database? e.g. Will a 200Gb database upgrade in essentially
> the same time window as a 20Gb database?
>
>
>
>
>
> Best Regards,
>
>
>
> Joel Patterson
> Database Administrator
> 904 727-2546
>
>
>

-- 
Andrew W. Kerber

'If at first you dont succeed, dont take up skydiving.'

--
http://www.freelists.org/webpage/oracle-l
Received on Mon Mar 15 2010 - 14:47:55 CDT